The New Winterstoke Hundred Academy, transforming a greenfield site into a modern net-zero secondary school for 900 pupils.
Winterstoke’s Academy was a new secondary school where Solum cooperated with KIER. Solum provided the groundworks on the former RAF Locking recreational grounds. With our support, the site transformed into a modern education facility. At the time work was first initiated, the neighbouring farmers’ fields were still filled with crops, but these would eventually become the future sports pitches for the students. Solum played a pivotal role in the groundworks package, and the building was successfully completed in November 2023. We completed the following work:
The Winterstoke academy was not without its share of challenges for Solum. Notable hurdles included:
To repurpose neighbouring fields into sports pitches, a cell web access track was constructed through a root protection zone. The cell web track allowed site vehicles to navigate through the root protection zone, ensuring the safety of the existing natural environment while facilitating the progression of earthworks.
The presence of overhead cables posed a significant challenge, with material being stockpiled strategically until they could be diverted by Western Power. Efficient stockpiling strategies were implemented to ensure the material’s readiness for redistribution once Western Power diverted the overhead cables.
Balancing construction needs with environmental preservation required Solum to adhere to ecological guidelines. We created attenuation ponds and new habitat zones, ensuring a commitment to sustainable construction.